Project Name
Cameron Park - Subdivision Road Rehabilitation Project
 
Project Type
Road Work
 
Project Description

Rehabilitation of the asphalt surface within the Cameron Park subdivision including the removal of the existing road surface, application of a new gravel base and a new asphalt road surface.

 
Impact to Residents

Residents can anticipate traffic disruptions during construction. One lane of traffic will be maintained during construction, but short-term full road closures may be required. In case of a road closure, or if access to a property will be impeded, affected residents will be notified in advance.

 
Project Status
  • October 2, 2019 – Landscaping (seeding) ongoing.
  • September 4, 2019 – Paving complete, remaining items include mailbox adjustments, road side-slope shaping, landscaping, topsoil placement and seeding.
  • August 28, 2019 – Paving underway, second lift of asphalt being placed.  Landscape restorations to follow.
  • August 21, 2019 - Gravel base completed, paving anticipated end of August (weather dependent). Landscape restorations to follow.
  • August 7, 2019 - Construction ongoing. October completion weather dependent
  • July 24, 2019 - Construction has started and should be completed by mid October.
  • July 10, 2019 - Preparing to start construction July 15 (weather dependent)
  • July 4, 2019 - Public Information Session held at Namao Hall
  • June 28, 2019 – Resident notification letter sent to residents
  • June 25, 2019 - Design complete, tender awarded (Council meeting)
 
Project Timeline
Construction anticipated to start July 15 (weather dependent) and should be completed October 2019.
 
Project Lead
Mark Guerette, Sr. Infrastructure Engineering Officer, 780-939-1324
 
Project Cost
$5.63 million budget for all 2019 Road Rehabilitation Projects (Rge Rd 242, Rge Rd 245, Cameron Park and Glenview Acres)