Project Name
Township Road 562 Reconstruction Project
 
Project Type
Road Work
 
Project Description

Road Work - Full reconstruction and surfacing of the portion of Township Road 562 from Hwy 2 to Range Road 253.

 
Impact to Residents

Residents can anticipate traffic disruptions during construction. One lane of traffic will be maintained during construction, but short-term full road closures may be required. In case of a road closure, or if access to a property will be impeded, affected residents will be notified in advance.

 
Project Status
  • October 2, 2019 – Project complete.
  • September 18, 2019 - Paving is complete. Minor ditch, grading, and landscape work remains. Construction activities are expected to be complete by October 15, 2019.
  • August 21, 2019 - Paving is complete. Ditch and minor grading work remain. Construction activities are expected to be complete by October 15, 2019
  • July 26, 2019 - Gravel and pavement construction to begin in early August
  • July 10, 2019 – Dirt work construction in progress
  • June 25 – Tender awarded, construction to start June 24
 
Project Timeline
Construction scheduled from June 24 to August 15 (weather dependent)
 
Project Cost
$523,500