Bridge engineering and maintenance work will take place on Township Road 544 west of Range Road 255.
Project file #BF85343
Project Update
October 15, 2021
Construction is complete.
October 8, 2021
Construction is underway.
October 1, 2021
Construction is underway.
September 24, 2021
No change.
September 20, 2021
Construction is scheduled to start the week of October 4, 2021.
September 13, 2021
Construction is anticipated to be complete by October 31, 2021.
September 7, 2021
Construction is underway, with completion anticipated by October 31, 2021.
August 2021
Land negotiations are ongoing