Township Road 544 from Highway 2 to ProNorth: road reconstruction

Township Road 544 from Highway 2 to ProNorth: road reconstruction

2174

Division 3

This summer, the parts of the following roadways will be reconstructed:

  • TWP 544    (HWY 2 to Elliot Street (Access to ProNorth)
  • RR 252     (HWY 37 to Coal Mine Road)

This project includes paving both roads with asphalt surfacing.

 

Project Update

July 4, 2022

The first lift of asphalt is done with the exception of one section requiring repairs on Rge Rd 252. Subgrade work on Twp Rd 544 ProNorth is in progress.

June 27, 2022

The first lift of asphalt on TWP RD 544 from the Firehall road is in progress. Subgrade work on Twp Rd 544 ProNorth is in progress.

 

June 13, 2022

Construction crews are finishing work near the south limits of the firehall. The equipment relocation and paving at ProNorth is scheduled to be done by the end of July.

November 26, 2021

2021 Construction season has ended. This project will carry over to 2022.

November 12, 2021

Utility relocation is in progress.

November 5, 2021

Work continues on the utility relocations.

October 29, 2021

Work continues on the utility relocations.

October 22, 2021

Bridge culvert installation complete. The utility relocation is in progress.

October 15, 2021

The milling is complete from Hwy 2 to RR260. Bridge culvert installation is complete.

October 8, 2021

The milling is complete from Hwy 2 to RR260. Bridge culvert installation will take place the week of October 12, 2021.

October 1, 2021

The milling is complete from Hwy 2 to RR260. Bridge culvert installation to commence October 1, 2021.

September 24, 2021

Brushing is complete. The milling is 50% complete.

September 20, 2021

This week, crews will begin milling away the top layers of asphalt from the road surface.

September 13, 2021

Construction start was delayed due to rain. The construction schedule is being finalized.

September 7, 2021

Construction is scheduled to start on September 14, with crews mobilizing equipment on-site by September 10, 2021.

August 2021

Construction will begin on August 30, 2021.

About the Project

This summer, the parts of the following roadways will be reconstructed:

  • TWP 544    (HWY 2 to Elliot Street (Access to ProNorth)
  • RR 252     (HWY 37 to Coal Mine Road)

Twp 544 is currently a paved surface and RR 252 is gravel surfaced. This project includes paving both roads with asphalt surfacing.

This project also includes:

  • Excavation of existing roadway
  • Re-grading the road right of way
  • 1.3km of Geocell reinforcement along TwpRd 544
  • Granular base course and use of Geosynthetics for the remainder of roadways
  • Asphalt surfacing for both projects
  • Earthworks construction of ditches and approaches
  • Topsoil and reclamation

 

Public Engagement

An information session was hosted on July 17, 2021, to discuss the project.
You can watch a recording of the session or view a PDF of the presentation.

 

Contact

For more information, contact the project manager Chris Pullen, Senior Industrial Engineering Officer, at 780-939-1319, or by email: cpullen@sturgeoncounty.ca