This summer, Sturgeon County contractors will be working on the drainage channel located in the County owned right-of-way in the neighbourhood. This work includes clearing the channel of vegetation, and re-grading and reinforcing the banks to improve drainage and prevent erosion of the channel.
During construction, residents can expect some noise and dust as a result of the work. As well, crews will be removing some trees and brush from the channel to improve the flow of water.
Please use caution when driving through the area, as construction vehicles will be parked along Estate Way to allow crews and equipment access to the site.
Project Update
November 12, 2021
Current status: Construction is complete.
November 5, 2021
This project is substantially complete.
October 29, 2021
Construction is underway, with the work about 98% complete.
October 22, 2021
Construction is underway, with the work about 98% complete.
October 15, 2021
Construction is underway. Grading work is complete, and rip rap is being installed.
October 8, 2021
Construction is underway. Grading work is complete, and rip rap is being installed.
October 1, 2021
Construction is starting today.
September 24, 2021
Scheduled to be complete by October 31, 2021.
September 20, 2021
Contractors are mobilizing on-site with construction starting this week.
September 13, 2021
Construction is anticipated to be complete by September 30, 2021.
September 7, 2021
Waiting for First Call locates. Targeting completion in fall 2021.
August 2021
Targeting September 30, 2021 completion.