This summer, Sturgeon County is beginning work in the Upper Manor Pointe Stage III subdivision to repair a number of drainage issues and perform maintenance on the site infrastructure.
Project Update
November 12, 2021
Current status: Construction is 90% complete.
October 29, 2021
Construction is 87% complete.
October 22, 2021
Construction is 85% complete.
October 15, 2021
Construction is 80% complete.
October 8, 2021
Construction is 75% complete.
October 1, 2021
Construction in progress; 70% complete.
September 24, 2021
Construction in progress; 65% complete.
September 20, 2021
Construction in progress; 50% complete.
September 13, 2021
Construction in progress
September 7, 2021
Construction in progress 30% complete
August 2021
Construction is in progress.
July 2021
An information session about the project was hosted on Wednesday, July 14, 2021, at 6 p.m.
Watch a recording of the meeting or view a PDF of the presentation to learn more about the work.
About the Project
This summer, Sturgeon County is beginning work in the Upper Manor Pointe Stage III subdivision. This project includes:
- Ditch restoration
- Four culvert replacements and driveway repairs
- Three culvert repairs
- Intermittent grading work
- Repainting the fence along Coalmine Road
Questions? Contact Sturgeon County offices, 780-939-8252 or email Roads@SturgeonCounty.ca