Meadowview Drive and RR 261A Road Rehabilitation
X

Projects Archive

<< Back to Archive Home

 


Meadowview Drive and RR 261A Road Rehabilitation

Meadowview Drive and RR 261A Road Rehabilitation

2680

Division 3

Portions of Meadowview Drive are undergoing rehabilitation as part of a multi-year project to repair the road surface and subgrade. Range Road 261A is being realigned due to erosion of the creek bank and rehabilitated to the north of Meadowview Drive.

 

Project Update

November 26, 2021

Current status: The 2021 construction season has ended. This project will carry over to 2022. 

November 12, 2021

The first lift of asphalt is complete. 

November 5, 2021

Construction is underway along Meadowview Drive, with 90% of the GBC work completed and paving starting today.

October 29, 2021

Construction is underway along Meadowview Drive, with 90% of the GBC work completed and paving starting today.

October 22, 2021

Construction is underway along Meadowview Drive, with 70% of the GBC work completed. All centerline culverts installations are complete, and approach culvert installations are in progress. On Range Road 261A, the paving is completed.

October 15, 2021

Along Meadowview Drive, 90% of subgrade work is complete. Crews are proceeding with culvert installations and progressing to prepare base course  On Range Road 261A, the paving is completed.

October 8, 2021

Along Meadowview Drive, 90% of subgrade work is complete. Crews are proceeding with culvert installations and progressing to prepare base course  On Range Road 261A, the paving is completed.

October 1, 2021

Along Meadowview Drive, 50% of subgrade work is complete.  On Range Road 261A, paving will begin on October 2, 2021.

September 24, 2021

Construction is underway. Along Meadowview Drive, crews have finished milling the top asphalt layers off of the roadway.  On Range Road 261A, subgrade work is underway.

September 20, 2021

Construction is underway. Along Meadowview Drive, crews have finished milling the top asphalt layers off of the roadway.  On Range Road 261A, crews are stripping the land to prepare the new roadway alignment and culvert installations.

September 10, 2021

Work started on September 9, 2021.

September 3, 2021

Work is anticipated to start the first week of September 2021.

The contract has been awarded to TBL Construction Ltd.

August 2021

The tender closed on August 10, 2021, and the contract has been awarded.

June 2021

An online information session was held on Thursday, June 10, 2021, to provide details about the preliminary design of the road rehabilitation. Topics discussed include:

  • Project scope and timeline
  • Anticipated construction activities

If you were unable to attend, you can watch a recording of the information session or view a PDF of the presentation for an overview of the work planned and to meet the project team.

 

About the Project

The rehabilitation work planned for Meadowview Drive will maintain the existing footprint of the roadway. This is a multi-year project which includes subgrade stabilization and resurfacing of the pavement. The full scope of work is estimated to cost $9 million.

In 2021, work is scheduled to be completed on 4 km of road between Range Road 261A and 263A. This includes full surfacing with hot-mix asphalt pavement. 

Additionally, approximately 500 m of cold-mix asphalt will be rejuvenated just east of Highway 44 on Meadowview Drive.

For more information, contact the project manager Gary Mayhew, Manager Transportation & Engineering Services, at 780-939-8260, or by email at gmayhew@sturgeoncounty.ca.