Alberta Transportation Projects May to October 2019
X

Road Report & Utility AlertsRoad Report & Utility Alerts

Alberta Transportation Projects May to October 2019

Alberta Transportation Projects May to October 2019

Courtesy Post

HWY 15/37/825 ROAD CONSTRUCTION: 2018/2019
Intersection of Hwy 37, Hwy 15 and Hwy 825 interchange – road construction currently taking place; with reduced speeds

HWY 2 FROM ST. ALBERT NORTH TO HWY 651:
May to October, 2019 Paving, Intersection and illumination improvement projects - road construction currently taking place; with reduced speeds

HWY 803/28 ROAD CONSTRUCTION:
May to October, 2019 Intersection improvement of Hwy 803 and Hwy 28 (north approx. 2km) – during road construction there will be one lane road closures with reduced speeds

HWY 28 FROM HWY 37 NORTH TO HWY 642 ROAD CONSTRUCTION:
May to October, 2019 Illumination improvement at Township Road 552 and 554 on Hwy 28; with reduced speeds

HWY 15 FROM EAST OF HWY 28A TO WEST OF HWY 37 ROAD CONSTRUCTION:
May to October, 2019 Highway twinning project - road construction currently taking place; with reduced speeds

If you have questions or concerns please contact Alberta Transportation at (780) 963-5711. These projects will begin at different times from May to October. Please drive with caution obeying all traffic accommodation to ensure the safety of the workers and travelling public.