Construction Updates – April 19, 2024

Access Fibre (runs by each premise in a subdivision, hamlet or industrial park)

  • CFOC is working to schedule the drilling equipment for this last area.
  • All other access construction is complete.

Drop fibre (connects the access fibre to the premise)

  • Most of the drops left require pipeline crossing agreements and special installation procedures.

Splicing (connecting the fiber segments into one continuous length)

  • The crossing in Pro North is still in progress, all other splicing is complete.

ONT installation (the last step before service is available to a premise)

  • ONT installations are being booked for communities included in Phase 1.
  • Once your drop installation is complete you are ready to contact Canadian Fibre Optics Corporation to have your Optical Network Terminal (ONT) installed and activated, 1-888-236-2947