Temporary Road Closures & Delays
X

Road Report & Utility AlertsRoad Report & Utility Alerts

Temporary Road Closures & Delays
Administrator Account

Temporary Road Closures & Delays

As of September 18, 2020

 

Sturgeon County may need to close roadways in the event of maintenance or construction. Please ensure the appropriate authorities are notified. Partial Closures will take place from 8 a.m. to 4:30 p.m. unless otherwise posted.

 

Partial & Full Lane Closures:

 

Lamoureux Drive – From Highway 15 to Boysdale Road

DATE: September 14, 2020 to October 15, 2020

Contractor will be performing drainage improvements in the area.

  • Mobilization to take place the week of September 7th.
  • Expect delays in traffic.
  • Traffic accommodation will be in place.

 

North Saskatchewan River Hwy 15 Bridge Project:

Alberta Transportation has contracted ALBERCO Construction for the Hwy 15 bridge project over the North Saskatchewan River. The contractor has a Traffic Accommodation Strategy in place which includes partial and full road closures. Advance warning signs will be installed.

If you have any questions the primary contact is Site Superintendent - Fred Klaszus (780) 267-5829.

Lamoureux Drive under the Hwy 15 bridge between the two ramp accesses onto Hwy 15

The road closures are scheduled as follows:

  • One Lane Closure: June 18 to September 25, 2020

Roseridge Road (Range Road 251) - from Hwy 642 south to Township Road 555

DATE: August 26, 2020 to October 15, 2020

Contractor will be performing road rehabilitation and stabilization on Rge Rd 251 from Hwy 642 south to Twp Rd 555

  • Mobilization to take place week of August 24, 2020
  • Possible one day temporary road closure for centerline culvert installation
  • Expect delays in traffic
  • Traffic accommodation will be in place

Bridge Maintenance Program: Contractors will be performing replacement repairs to the following three bridge locations:

DATE: July 27, 2020 to October 31, 2020

1. BF558 - Bridge Culvert Replacement - on Range Road 230, south of Township Road 560 - COMPLETE

  • Road is open, cleanup in progress

2. BF9433 - Bridge Culvert Line Installation - on Township Road 582, east of Range Road 244

  • Mobilization planned for October 5, 2020
  • One Lane Closure – October 5, to October 16, 2020

3.  BF76322 - Bridge Culvert Replacement - on Township Road 565, east of Range Road 262

  • Mobilization planned for September 28, 2020
  • ROAD CLOSURE - September 28, 2020 to October 23, 2020
  • No through traffic on Township Road 565 between Range Road 261 and Range Road 262
  • DETOUR:  South on Range Road 261 or Range Road 262 and east or west of Township Toad 564

Enhanced Road Maintenance Program - Contracted road repairs and stabilization to repair damage due to spring thaw and flooding.

DATE: August 24, 2020 to October 31, 2020 (weather permitting)

Doblanko Contracting Ltd. will be performing the enhanced road maintenance at the following locations; please be prepared for traffic delays and unexpected road closures.

  • Township Road 580 - from Range Road 244 to Range Road 245 - COMPLETE
  • Range Road 234 - from Hwy 28 to Township Road 564 - COMPLETE
  • Township Road 562 - from Range Road 244 to Range Road 252 - COMPLETE
  • Range Road 245 - from Hwy 642 to Township Road 562 - IN PROGRESS
  • Range Road 245 - from Township Road 551 to Township Road 554 - IN PROGRESS
  • Township Road 562 - from Range Road 255 to Range Road 261
  • Range Road 260 - from Hwy 642 to Township Road 562

 

DATE:  September 8, 2020 to October 31, 2020 (weather permitting)

TBL Construction Ltd. will be performing the enhanced road maintenance at the following locations; please be prepared for traffic delays and unexpected road closures.

  • Range Road 233 – from Hwy 651 to Township Road 575A - IN PROGRESS
    • Road closure - open to local traffic only (residents)
  • Range Road 205 – from Township Road 574 to Township Road 580 - IN PROGRESS
    • Road closure currently in effect until further notice
    • No through traffic
  • Range Road 211 – from Township Road 574 to Township Road 580
  • Range Road 204 – from Township Road 574 to Township Road 580 - IN PROGRESS
    • Road closure - open to local traffic only (residents)
  • Range Road 223 – from Township Road 570 to Township Road 572
  • Range Road 244 – from Township Road 580 to Township Road 582
  • Township Road 564 – from Range Road 240 to Range Road 241
  • Township Road 564 and Range Road 241 - Intersection
  • Township Road 551 – from Range Road 234A to Range Road 235
  • Township Road 543 – from Hwy 44 to Range Road 270
  • Township Road 540 – from Range Road 262 west to Range Road 263

 


Full Road Closures:

 

TOWNSHIP ROAD 565 between RANGE ROAD 262 AND RANGE ROAD 263

DATE:  Monday September 21, 2020 (weather permitting)

PROJECT:  Contractor will be performing a culvert replacement due to a collapsed culvert.

  • No through traffic during excavation
  • Road anticipated to be open by 6:00 p.m.
  • DETOUR: 
    • Residents east of work area must access from Range Road 262
    • Residents west of work area must access from Range Road 263

 

NAMAO RIDGE SUBDIVISION – south off of TOWNSHIP ROAD 554 on SHULTZ DRIVE

DATE:  Monday September 14, 2020 to Monday September 21, 2020 (weather permitting)

Contractor will be performing drainage work along Shultz Drive between the north and south intersections onto Shultz Crescent

  • No through traffic during work hours – road will be open and equipment off the road during the evening and night time
  • Signage is in place – detour signs for local traffic only and barricades and delineators in construction zone
  • DETOUR:  Residents must use Shultz Crescent travelling through subdivision; local residents on Shultz Drive will have access to their homes

 

 


 


Partial Road Closures & Delays:

 

TOWNSHIP ROAD 554 (RQB) from RANGE ROAD 265 west approximately 340m – ONE LANE TRAFFIC

DATE:   Wednesday September 9, 2020 to Sunday September 22, 2020

Contractor will be performing drainage work along this section of roadway

  • Eastbound lane will be closed
  • Expect traffic delays
  • Signage will be in place Tuesday September 8, 2020

 

Campbell Scientific will be installing frost probes for Transportation Services during the week of September 14, 2020 at the following 3 locations:

Details are as follows:

  • All closures will be from 8:00 a.m. to 6:00 p.m.
  • There will be one lane closure during the installation
  • Traffic controls will be in place
  • Expect traffic delays

Location 1: Cardiff Road (Twp Rd 554) approximately .5 km east of Range Road 250

Date: To be determined

  • Eastbound lane will be closed

Location 2: Lily Lake Road (Rge Rd 235) approximately 1 km south of Township Road 570

Date: To be determined

  • Northbound lane will be closed

Location 3:  Opal Road (Rge Rd 224) approximately 0.8 km north of Hwy 643

Date:  To be determined

  • Southbound lane will be closed

Starkey Road (Rge Rd 251) - from Hwy 37 to south of Coal Mind Road; and Starkey Road/Sturgeon Road Intersection:

Contractor will be performing the following two projects:

Location 1: Starkey Road - from Hwy 37 to south of Coal Mine Road - road rehabilitation at this location

  • Work to begin at Hwy 37 to south of Coal Mine Road
  • Expect delays in traffic

Location 2: Starkey Road/Sturgeon Road - intersection improvements at this location

  • Expect delays in traffic 

DATE:    Monday, August 17, 2020 to September 30, 2020 (weather permitting)


Township Road 544 - from Range Road 275 to Range Road 280 and Hansen Estates Subdivision:

Contractor will be performing road rehabilitation at this location

  • Work to begin in the Hansen Estates subdivision and carry on to Twp Rd 544 from Rge Rd 275 to Rge Rd 280
  • Expect delays in traffic

DATE:    Monday, August 17, 2020 to October 16, 2020 (weather permitting)


 


Township Road 551 between 24508 and 24516 - One Lane Traffic:

Due to water encroaching onto the road on both shoulders of the road at this location there will be one lane traffic through this area.

  • Barriers will be placed where the roadway narrows
  • Signage will be placed at each end of the reduced lane area

DATE:    Effective immediately - Wednesday, July 8, 2020


Hwy 642/Range Road 255 Intersection Upgrades Project:

Willows Construction on behalf of G3 will be performing intersection upgrades at Hwy 642 and Range Road 255.

  • Construction of a Type IIIb intersection and upgrading of 300m of Rge Rd 255 going north of Hwy 642
  • Expect delays in traffic – there will be lane restrictions during construction
  • Flaggers will be onsite for traffic control
  • No full road closures anticipated

DATE:    Monday July 6, 2020 to Friday September 25, 2020 (weather permitting)


 

 

 