Update as of June 1, 2018

Sturgeon County Capital ProjectsSturgeon County Capital Projects

Division Map

All Divisions

Project
Project Status
Local Road Reconstruction Program (LRRP)
Road Work - Preliminary Engineering
RFP for Program Engineer closed March 29, 2018, evaluation of submissions completed. RFD to award contract for Program Engineer scheduled for May 8, 2018.

Division 1

Project
Project Status
Bridge File 85330 - Intersection Hwy 825 Rge Rd 224A
Bridge Work - Bridge File Replacement
Being constructed as a part of the Highway 825 / RgeRd224A Intersection improvement. Alberta Transportation is leading this project.
Bridge File 85149 - Intersection Hwy 825 Rge Rd 224A
Bridge Work - Bridge File Replacement
Being constructed as a part of the Highway 825 / RgeRd 224A Intersection improvement. Alberta Transportation is leading this project.
Bridge File 559 - Intersection Hwy 825 Rge Rd 224A
Bridge Work - Bridge File Replacement
Being constructed as a part of the Highway 825 / RgeRd224A Intersection improvement. Alberta Transportation is leading this project.
Allin Ridge Reservoir/Pumphouse
Drainage Work - Reservoir Expansion/Pumphouse Upgrades
Substantial completion received. Requires cleanup of minor deficiencies
Lamoureux Drive Drainage
Drainage Work - Road realignment and drainage improvements
Phase 1 of project is substantially complete, phase 2 currently planned for 2020. Additional guard rail installation is to be completed in 2018.
Riverside Park Drainage
Drainage Work - Drainage Improvement
Minor warranty work
Intersection - Hwy 825 & Rge Rd 224A
Road Work - Reconstruct/Pave
Developer Front ended Design / Land / Contingency Dollars
Rge Rd 241 - Cameron Park to Twp Rd 552
Road Work - Phase 1 - Reconstruct for surfacing (2.3 km)
Reconstruction is now complete. Landscaping ditches and second lift of asphalt remains to be completed along Twp. Road 552 approaches.
Fort Augustus Access - Rge Rd 233: From Boysdayle Road to Lamoureux Drive
Road Work - Rehabilitation
Project delayed due to funding constraints
Riverside Park - Subdivision
Road Work - Rehabilitation
Project delayed due to funding constraints
Rge Rd 245 - Glenview Access: From 195th Ave to Glenview Place
Road Work - Rehabilitation
Project delayed due to funding constraints
Glenview Place and Glenview South Subdivisions
Road Work - Rehabilitation
Project delayed due to funding constraints
Rge Rd 232 - Pilon Creek Estates Access: From Hwy 15 to 1km North
Road Work - Rehabilitation
Construction to begin summer 2018
Pilon Creek Estates - Subdivision
Road Work - Rehabilitation
Construction to begin summer 2018
Crestview Heights - Subdivision
Road Work - Rehabilitation
Preliminary engineering underway.
Fort Augustus - Subdivision
Road Work - Rehabilitation
Preliminary engineering underway.
Rge Rd 242: From Twp Rd 554 to Schultz Drive (Grandview)
Road Work - Rehabilitation
Detailed design complete
Rge Rd 241: From Cameron Park to Twp Rd 552 (Collector)
Road Work - Phase 2 - Surfacing
Complete.
Twp Rd 552: From Rge Rd 241 to Rge Rd 240
Road Work - Phase 2 - Surfacing
Paving of driving lanes is complete. 2nd lift of asphalt remains outstanding on some approaches. Winter shut down meeting scheduled for November 7.

Division 2

Project
Project Status
Estate Way Drainage
Drainage Work - Drainage improvements
Deficiencies remain from work that was completed in 2016, planned for completion in 2018
Rivers Gate Lift Station
Drainage Work - New Lift Station Construction
Sustantial Completion Received. Monitoring during warranty period.
Cardiff Road Improvements Project
Road Work - Cardiff Road Project
Minor touch-ups and trail work in 2018 Construction Season.

Division 3

Project
Project Status
Bridge File 76320
Bridge Work - Bridge Culvert Replacement
Project delayed until 2019 due to land Acquisition, detailed design complete. Funding allocated to BF 9421
Villeneuve Drainage Channel
Drainage Work - Detailed Design of Drainage Channel. Survey Complete.
Contract to be awarded to MPA Engineering Ltd. Hamlet Public Open House complete. Data is being reviewed and modeling underway for hydrology and hydraulic options. Deliverables -Channel design report and Drainage Study. Draft reports expected Sept 14, 2018.
Hamlet of Villeneuve Drainage Study
Drainage Work - More Info Coming Soon
Public Notification underway. Public open house planned for June (date TBD). Draft design report scheduled for October 2018.
Meadowview Drive - (Base/Pave)
Road Work - Roadwork-Engineering Contract awarded, preliminary design starts on Sept 10, 2018
Design to start.
Twp Rd 544: From Rge Rd 280 to Rge Rd 275
Road Work - Rehabilitation
Project delayed due to funding constraints
Terrault Estates - Subdivision
Road Work - Rehabilitation
Project delayed due to funding constraints
Pinesands Subdivision
Road Work - Rehabilitation
Preliminary engineering underway.
Glory Hills Subdivision
Road Work - Rehabilitation
Detailed design complete.
Hansen-Subdivision
Road Work - Rehabilitation
Detailed design complete.

Division 4

Project
Project Status
Bridge File 76321
Bridge Work - Bridge Culvert Replacement.
Bridge replacement. Construction targeted for 2018. Construction Contract to be awarded to In Line Contracting Partnership. Construction summer 2018. Construction schedule Sept 04-18, 2018. The road will be closed during this timeframe.
Bridge File 9421
Bridge Work - Bridge Culvert Replacement.
Bridge replacement. Construction Contract to be awarded to In Line Contracting Partnership. Construction summer 2018. Construction scheduled from Sept 19-28. The road will be closed during this time frame.
Riviere Que Barre Drainage
Drainage Work - Drainage improvements within the RQB hamlet
Drainage Improvement in RQB Hamlet. Tender closed, consultant is evaluating bids. Construction in 2018 and 2019
RQB - Trans Corridor Improvement
Drainage Work - Crosswalk and drainage improvements
Contractor was unable to complete construction in 2017, will resume in May/June 2018
Alcomdale Waterline
Water Work - New waterline to Alcomdale
Reservoir has been commission. Work is 90% complete. Boil Water Advisory still in affect.

Division 5

Project
Project Status
Lily Lake Area Projects
Bridge Work - Reconstruction and Surfacing / Bridges—(OPUS – Consultant) (E-Construction - Paving Contactor), (Caburn Construction – Grading Contractor)
TWP 570 + RR233 Construction is underway and will continue through the construction season. Paving crew is scheduled to mobilize the week of October 1st to begin paving operations. TWP 572: Road to be closed between Rge Rd 233 and Hwy 28 Construction is underway and will continue through the construction season. Open to local traffic only. The intersection of Hwy 28, Rge Rd 232, and Twp Rd 572 will open on September 19th. Twp Rd 572 from Rge Rd 232 to Rge Rd 233 will be closed until September 28th
Bridge File 9433 (SW-16-58-24-W4)
Bridge Work - Bridge Culvert Replacement.
Budgeted for 2019 construction, detailed design in 2018
Twp Rd 562: From Rge Rd 253 to Hwy 2 (Base/Pave)
Road Work - Reconstruction and Surfacing
RFP for Engineering service to go out Summer 2018
Freemore Estates - Subdivision
Road Work - Rehabilitation
Preliminary engineering underway.

Division 6

Project
Project Status
Traffic Signals - Intersection HWY 825 & 643
Road Work - Traffic Signal Installation Hwy 825 / Hwy 643
Construction Completion Certificate has been issued. Signals are currently under warranty. Once warranty expires, signals will be turned over to Alberta Transportation.
Rge Rd 212 - Hwy 38 to Hwy 644
Road Work - Phase 1 - Reconstruct for gravel surface (6.4 km)
Under review
Sturgeon Valley Estates - Subdivision
Road Work - Rehabilitation
Preliminary engineering underway.
Twp Rd 564 - Hwy 28A to Rge Rd 231
Road Work - Reconstruction and Surfacing
Currently working with CN for approval to lower road grade beneath bridge structure.
Rge Rd 220 / Hwy 643 Intersection Improvements
Road Work - Tendering of project is complete. Voice construction is completing upgrades in 2018.
Onsite