Sturgeon County - Engineering Projects
X

Sturgeon County ProjectsSturgeon County Projects

Back
Division
Division 4
 
Project Name
Riviere Que Barre Drainage Project - Phase 2
 
Project Type
Drainage Work
 
Project Description

Drainage improvements within the RQB hamlet

 
Impact to Residents

To be determined

 
Project Status
  • September 18, 2019 – Construction ongoing, anticipate October completion
  • July 10, 2019 - Construction underway, anticipate October completion
 
Project Timeline
2019 Construction Schedule
 
Project Lead
Gary Mayhew, Manager, Transportation Services, 780-939-8260
 
Project Cost
$1.09 million