Project Name
Hwy 2 & Cardiff Road Waterline
 
Project Type
Water Work
 
Project Description

Water Work: Sturgeon County is presently working with a contractor to relocate a portion of the RQB waterline near the intersection of Cardiff Road and Hwy 2.

 
Impact to Residents

Intermittent water shutdowns will be required for short periods of time. Residents along the RQB and Alcomdale waterline who are tied into the water system should ensure that their cisterns are topped up each day.

 
Project Status
  • September 18, 2019 - Project is 90% complete, completion end of September (weather dependent)
  • August 7, 2019 - Project is 60% complete, completion end of August (weather dependent)
  • June 10, 2019 – Work has begun and will continue until the end of August (date approximate)
  • June 2019 – Notification letters sent to affected residents on the RQB waterline
 
Project Timeline
The work has begun and will be taking place until the end of August (weather permitting).
 
Project Lead
Roger Borchert, Utility Capital Projects Officer, ph. 780-939-1302
 
Project Cost
Unknown