Starting in late September, Sturgeon County contractors will be working to develop a new approach and expand the parking lot at Bellerose Park.

The work will be completed in two phases:

  1. 2021: Creating a new, larger gravelled parking lot to accommodate 45 vehicles, relocating the approach to the parking lot, and installing an asphalt trail connection from the parking lot to the trailhead.
  2. 2022: Final landscaping work and tree installation.

During construction, the trails, and the existing parking area with remain open to the public.

Construction will take place Monday through Saturday from 7 a.m. to 7 p.m.  There may be some minor traffic disruptions when the new parking lot approach is constructed. 

 

Questions?

Contact Agriculture Services by email agricultureservices@sturgeoncounty.ca or call 780-939-8349 

 

Project Update

October 29, 2021

Construction is complete.

October 1, 2021

Construction is underway. 

September 20, 2021

The contract has been awarded and construction is scheduled to start on September 27, 2021.

September 13, 2021

Proposals in review. The contract will be awarded shortly.

September 7, 2021

Awaiting quotes from contractors on the design concept.

August 2021

The project is currently in the Design Phase, with many project details such as dimensions, features and materials being finalized.

A tender has not been posted.

The contract for the work has not been awarded.