Benjamin Road from Hewett Drive North - Thin Lift Overlay
X

Benjamin Road from Hewett Drive North - Thin Lift Overlay

968

Division 5

Pavement preservation with a Thin Lift Asphalt Overlay is planned for Benjamin Road from Hewett Drive North for 1.8 km.

This work is part of a pavement preservation program that includes several other subdivisions in Sturgeon County. Crews will be moving from location to location over the course of the month.

 

Learn more about the Thin Lift Asphalt Overlay process.

 

Project Update

November 5, 2021

Current status: This project is complete.

October 29, 2021

Scheduled for completion in the coming week. There were some delays due to rain earlier this week.

October 22, 2021

Scheduled for completion by October 31, 2021.

October 15, 2021

Scheduled for completion by October 31, 2021.

October 8, 2021

Scheduled for completion by October 31, 2021.

October 1, 2021

Scheduled for completion by October 31, 2021.

September 24, 2021

Construction work on the Pavement Preservation program is anticipated to start the week of October 4, 2021, with crews travelling to work sites in the following order:

  1. Green Acres
  2. Manor Estates
  3. Upper Viscount
  4. Sturgeon Road East
  5. Twp Rd 554
  6. Benjamin Road
September 13, 2021

This project is now scheduled to start on October 14, 2021, and is expected to take five days to complete.

September 7, 2021

This project is scheduled to start on October 7, 2021, and is expected to take five days to complete.

August 2021

The tender has closed and the contract has been awarded. 

Construction is scheduled to begin in mid-September and be complete by Fall 2021.