Bridge work will take place at Range Road 224, South of Township Road 572.

An engineering study is planned for the project. 

 

Project Update

November 12, 2021

Current status: RFP is being evaluated.

November 5, 2021

RFP is being evaluated.

October 29, 2021

RFP is being evaluated.

October 22, 2021

RFP closing is extended until October 26, 2021.

October 15, 2021

RFP is extended. It now closes on October 20, 2021.

October 8, 2021

RFP closes Friday, October 15, 2021.

October 1, 2021

No change.

September 2021

Draft RFP is underway. There is no scheduled start date for construction.

August 2021

Draft RFP is underway.