A culvert washout led to an emergency bridge replacement at 54227 Range Road 263
Project Update
November 12, 2021
Current status: Construction is underway with work about 85% complete.
November 5, 2021
Construction is underway with work about 70% complete.
October 29, 2021
Construction is underway with work about 10% complete. There were some delays due to rain earlier this week.
October 22, 2021
Construction is underway with work about 10% complete.
October 15, 2021
Construction is scheduled to start the week of October 18t, 2021.
October 8, 2021
Scheduled for completion by October 31, 2021.
October 1, 2021
Scheduled for completion by October 31, 2021.
September 24, 2021
Scheduled for completion by October 31, 2021.
September 20, 2021
Scheduled for completion by October 31, 2021.
September 13, 2021
No change.
September 7, 2021
Legal review of the land agreement is underway.
September 1, 2021
Land negotiations are ongoing.
August 2021
Land negotiations are ongoing.