This summer, the following roadways will be reconstructed and surfaced:
- Heritage Drive (Heritage Industrial Park)
- Range Road 254 (From Highway 642 south approx. 725 m
Work being done on these roads includes:
- Reconstruction of the roadways to a finished pavement surface.
- Ditches will be reconstructed to improve stormwater conveyance.
For more information, contact Chris Longoz, Acting Senior Capital Projects Officer, at 780-939-1306, or by email at clongoz@sturgeoncounty.ca.
Project Update
November 26, 2021
Current status: Paving is complete.
The 2021 construction season has ended. Any remaining finishing or landscaping work will carry over to 2022.
November 12, 2021
The paving is 95% complete.
November 5, 2021
Construction is underway with paving along RR254.
October 29, 2021
Construction is underway with paving starting on RR254 today.
October 22, 2021
Construction is underway with the subgrade work 85% complete.
October 15, 2021
Construction is underway with the subgrade work 75% complete.
October 8, 2021
Construction is underway with the subgrade work 60% complete.
October 1, 2021
Subgrade prep is complete from Hwy 642 to the rail crossing.
September 24, 2021
Construction is underway. Along RR 254, topsoil stripping is underway.
September 20, 2021
Along RR 254, topsoil stripping is underway.
September 13, 2021
Construction is underway.
September 7, 2021
Construction is set to begin today.
August 30, 2021
Construction is to begin on September 7, 2021
About the Project
Information session
An information session was held on Thursday, June 3, 2021. Watch a recording of the information session or view a PDF of the presentation for an overview of the work planned and to meet the project team.
Questions? Contact Chris Longoz, Acting Senior Capital Projects Officer, at 780-939-1306 or by email at clongoz@sturgeoncounty.ca