Pine Sands: road Reconstruction
X

Pine Sands: road Reconstruction

1996

Division 3

This summer, Sturgeon County is starting work to reconstruct and pave the roads in the Pine Sands subdivision. 

Project Update

June 27, 2022

Notices have been sent to residents.

June 13, 2022
Construction is scheduled to begin mid July 2022.
 
November 26, 2021

Current status: The 2021 construction season is complete. This project will carry over to 2022.

November 12, 2021

Work continues to resolve the utility conflicts, Contractor mobilization discussion is in progress.

November 5, 2021

Work continues to resolve the utility conflicts, Contractor mobilization discussion is in progress.

October 29, 2021

Work continues to resolve the utility conflicts, Contractor mobilization discussion is in progress.

October 22, 2021

Work continues to resolve the utility conflicts, Contractor mobilization discussion is in progress.

October 15, 2021

Discussions about when the contractor can mobilize are in progress. Conflicts with utility line locations still exist.

October 8, 2021

Discussions about when the contractor can mobilize are in progress. Conflicts with utility line locations still exist.

October 1, 2021

Discussions about when the contractor can mobilize are in progress.

September 24, 2021

Mulching is complete. Utility relocation is in progress.

September 20, 2021

Crews are clearing brush in preparation for the earthwork.

September 13, 2021

Crews are clearing brush in preparation for the earthwork.

September 7, 2021

Construction is scheduled to start in mid-September.

August 30, 2021

Construction is scheduled to start in mid-September.

August 20, 2021

Prep work is underway, with construction scheduled to begin in early September.

The tender for this project closed on August 6, 2021, and the work has been awarded to TBL Construction Ltd.

 

About the Project

The work in Pine Sands includes:

  • Earthworks and grading within the right-of-way
  • Paving of Pine Drive and 6 cul-de-sacs in the subdivision
  • Paving driveway access to the property line
  • New signs
  • Paved pull out for mailbox access

 

What to expect during construction:

Construction will typically be underway between the hours of 7 a.m. and 8 p.m., Monday through Sunday. 

During construction, there will be an alternating single-lane of traffic, temporary traffic pauses using flag personnel, and other minor travel delays. Residents will be notified in advance of any road closures or if construction may block access to your property.  

 

Information Session

An information session about this project was held on Wednesday, June 30, 2021. You can watch a recording of the presentation here. 

The project was designed by WSP Engineering, to meets or exceed current standards. The current roadways are a mixture of paved and gravel surfaces with varying roadway widths, gravel thickness and ditch types.

If you have any questions or concerns, please contact Kevin Coyne, Capital Projects Officer at 780-940-7182 or by email kcoyne@sturgeoncounty.ca