Preliminary Engineering studies are planned for the rehabilitation of a section of Range Road 234  between Township Road 560 and Highway 28.

Residents may see surveyors out staking and crews locating utility lines to plan for construction. 

Project Update

November 2021

The detailed design is complete, and a review is in progress. There is no start date scheduled for construction.

September 2021

Detailed design drawings are underway. This project is in the engineering design phase. There is no start date scheduled for construction.

August 2021

Preliminary engineering and design work are underway.