Work will include reconstruction and surfacing of Range Road 234 from Highway 28 to Township Road 560, providing paved access to the Nywenning subdivision. Construction is planned to begin in 2022.

Project Update

July 5, 2022

Site grading is in progress. Project ID signs have been placed.

June 20, 2022

Land agreements have been signed. Stripping is underway, and project identification signs have been placed.