Range Road 244 is undergoing preparation of the 500 mm subgrade as crews are working to completely rebuilt the roadway.
These project photos were taken the week of August 9, 2021.
Project Update
October 8, 2021
The project is complete.
October 1, 2021
The project is 99% complete.
September 24, 2021
Construction is underway. The project is 99% complete.
September 20, 2021
Construction is underway. The project is 90% complete.
September 13, 2021
Construction is underway.
September 7, 2021
Construction is underway.
August 30, 2021
Construction is underway.