The existing paved roadway on the Southern portion of Starkey Road, and Range Road 244 from Highway 37 to CFB Edmonton will be rehabilitated using a technique known as Mill and Fill. As the name infers, this is where the existing roadways are first milled and then subsequently repaved to replace the asphalt which was milled away. Construction is planned to commence in 2022.



Project Update
July 18, 2022
The project is now scheduled to begin in August.
July 5, 2022
Work is scheduled to begin the second week of July.
June 20, 2022
The contract has been awarded.