Riviere Qui Barre Road Rehabilitation
X

Riviere Qui Barre Road Rehabilitation

1342

Division 4

The project is focusing on the two main roads in RQB, which are Township Road 554 from West of Range Road 265 to Highway 44 and Township Road 554 from South of Range Road 265 to Highway 44. We are also repaving the water fill station entrance loop. The rehabilitation work planned for Township Road 554 and Range Road 265 will maintain the existing footprint of the roadway. The construction methodology will be as follows:

  • Pulverize the existing road material.
  • Stabilize the pulverized material
  • Place a layer of granular base course.
  • Finish the surface with a layer of asphalt.

The full scope of work is estimated to cost $2.2 million. 

 

WSP is the consultant for the project and E-Construction will be the contractor.

 

For more information contact

David Becker
Capital Projects Officer
780-939-1320
dbecker@sturgeoncounty.ca

 

 

Project Update

October 15, 2021

Current status: The project is complete. 

October 1, 2021

The project is complete. Painting of speed bumps is scheduled for the week of October 11, 2021.

September 24, 2021

Painting of speed bumps is scheduled for the week of October 11, 2021.

September 10, 2021

The project is complete.

September 3, 2021

The project is 98% complete.

August 2021

The project is 80% complete.

It is in the construction phase, with paving underway.

Start date: July 12, 2021

 

 