Starkey Road - south portion: pavement preservation
X

Starkey Road - south portion: pavement preservation

593

Division 1

The existing paved roadway on the Southern portion of Starkey Road, and Range Road 244 from Highway 37 to CFB Edmonton will be rehabilitated using a technique known as Mill and Fill. As the name infers, this is where the existing roadways are first milled and then subsequently repaved to replace the asphalt which was milled away. Construction is planned to commence in 2022.

Project Update

July 25, 2022

The project is done.

July 11, 2022

The paving is done, line painting will follow.

June 27, 2022

The project is scheduled to start June 28, 2022 with completion in 2022.

June 20, 2022

The contract has been awarded. The project is scheduled to be completed in 2022.

Share