The roadways within Sturgeon View Crescent from Twp 542A will undergo pavement preservation treatment with a Thin Lift Asphalt Overlay. 

This work is part of a pavement preservation program that includes several other subdivisions in Sturgeon County. Crews will be moving from location to location over the course of the month.

Learn more about the Thin Lift Asphalt Overlay process.

 

Project Update

October 22, 2021

Paving complete.

October 15, 2021

Scheduled for completion by October 31, 2021.

October 8, 2021

Scheduled for completion by October 31, 2021.

October 1, 2021

Construction is scheduled to be complete by October 31, 2021.

September 24, 2021

Construction is scheduled to be complete by October 31, 2021.

September 13, 2021

Construction is now scheduled to start on September 24, 2021.

September 7, 2021

Construction is scheduled to start on September 18, 2021.

August 2021

The tender has closed, and the contract has been awarded. 

Construction is scheduled to begin in mid-September and be complete by Fall 2021.