Currently, a slope failure exists along the upper bank of Crozier Drive, along the entrance to Crossing at River’s Edge Subdivision.

The County is enlisting the services of a consultant to design a repair and prevention strategy that meets the natural character and esthetics found in the local area.

Project Update

December 3, 2021

Current status: Work is complete.

November 12, 2021

Work is approximately 85% complete.

November 5, 2021

Work is anticipated to be complete by November 12, 2021.

October 29, 2021

Construction is underway. Work is anticipated to be complete by November 12, 2021.

October 22, 2021

Construction is underway.

October 15, 2021

The construction kick-off meeting was held today.

October 8, 2021

The project is out for tender. Anticipate completion by October 31, 2021.

October 1, 2021

The project is out for tender. Anticipate completion by October 31, 2021.

September 24, 2021

The design review has been completed.

September 20, 2021

The design review is underway.

September 13, 2021

Tender package review underway.

September 7, 2021

Tender package review underway.

August 2021

The RFQ for design closes on September 1, 2021. 

The RFQ for a contractor will be issued shortly. 