Township Road 554 from Hwy 28 East to Grandview Heights - Thin Lift Overlay
X

Township Road 554 from Hwy 28 East to Grandview Heights - Thin Lift Overlay

1295

Division 5

Pavement preservation treatment with a Thin Lift Asphalt Overlay is planned for 2.3 km along Township Road 554 from Highway 28 to Grandview Heights. 

This work is part of a pavement preservation program that includes several other roads and subdivisions in Sturgeon County. Crews will be moving from location to location over the course of the month.

Learn more about the Thin Lift Asphalt Overlay process.

 

Project Update

October 29, 2021

The paving is complete.

October 22, 2021

Scheduled for completion by October 31, 2021.

October 15, 2021

Scheduled for completion by October 31, 2021.

October 8, 2021

Scheduled for completion by October 31, 2021.

October 1, 2021

Scheduled for completion by October 31, 2021.

September 24, 2021

Construction work on the Pavement Preservation program is anticipated to start the week of October 4, 2021, with crews travelling to work sites in the following order:

  1. Green Acres
  2. Manor Estates
  3. Upper Viscount
  4. Sturgeon Road East
  5. Twp Rd 554
  6. Benjamin Road
September 13, 2021

This project is now scheduled to start on October 6, 2021,

September 7, 2021

This project is scheduled to start on September 29, 2021, and is expected to take seven days to complete.

August 2021

The tender has closed and the contract has been awarded. 

Construction is scheduled to begin in mid-September and be complete by Fall 2021.

Township Road 554 from Hwy 28 East to Grandview Heights - Thin Lift Overlay

Share

Print