As part of the Local Road Program, road rehabilitation is underway between Riviere Qui Barre and Range Road 270
Learn more about the Local Roads Program here.
Project Update
October 22, 2021
Construction is complete.
October 15, 2021
Construction is 90% complete.
October 8, 2021
Construction is underway with the work 40% complete.
October 1, 2021
Scheduled to be complete by October 31, 2021.
September 24, 2021
Scheduled to be complete by October 31, 2021.
September 20, 2021
Scheduled to be complete by October 31, 2021.
September 13, 2021
No change.
September 7, 2021
No start date has been set.
Scheduled for completion by October 31, 2021.
August 30, 2021
The contract has been awarded.
The construction start date is dependant upon the contractor's availability.