Township Road 570 between Range Road 233 and 235
X

Township Road 570 between Range Road 233 and 235

1109

Division 5

As part of the Local Roads Program, road rehabilitation is planned along Township Road 570 between Range Road 233 and 235.

Learn more about the Local Roads Program here.

 

Project Update

October 22, 2021

The project is complete.

October 15, 2021

The project is approximately 95% complete.

October 8, 2021

The project is approximately 70% complete.

October 1, 2021

The project is approximately 40% complete.

September 24, 2021

No change.

September 20, 2021

Construction is underway. The project is about 10% complete.

September 13, 2021

Construction is scheduled to start in mid-September.

September 7, 2021

Construction is scheduled to start in mid-September.

August 30, 2021

The contract has been awarded.

Township Road 570 between Range Road 233 and 235

Share

Print