As part of the Local Roads Program, road rehabilitation is planned along Township Road 570 between Range Road 233 and 235.
Learn more about the Local Roads Program here.
Project Update
October 22, 2021
The project is complete.
October 15, 2021
The project is approximately 95% complete.
October 8, 2021
The project is approximately 70% complete.
October 1, 2021
The project is approximately 40% complete.
September 24, 2021
No change.
September 20, 2021
Construction is underway. The project is about 10% complete.
September 13, 2021
Construction is scheduled to start in mid-September.
September 7, 2021
Construction is scheduled to start in mid-September.
August 30, 2021
The contract has been awarded.