Upper Manor Pointe Stage III Drainage Improvements
X

Upper Manor Pointe Stage III Drainage Improvements

1862

Division 2

This summer, Sturgeon County is beginning work in the Upper Manor Pointe Stage III subdivision to repair a number of drainage issues and perform maintenance on the site infrastructure.

Project Update

November 12, 2021

Current status: Construction is 90% complete.

October 29, 2021

Construction is 87% complete.

October 22, 2021

Construction is 85% complete.

October 15, 2021

Construction is 80% complete.

October 8, 2021

Construction is 75% complete.

October 1, 2021

Construction in progress; 70% complete.

September 24, 2021

Construction in progress; 65% complete.

September 20, 2021

Construction in progress; 50% complete.

September 13, 2021

Construction in progress

September 7, 2021

Construction in progress 30% complete

August 2021

Construction is in progress.

July 2021

An information session about the project was hosted on Wednesday, July 14, 2021, at 6 p.m. 

Watch a recording of the meeting or view a PDF of the presentation to learn more about the work.
 

About the Project

This summer, Sturgeon County is beginning work in the Upper Manor Pointe Stage III subdivision. This project includes:

  • Ditch restoration
  • Four culvert replacements and driveway repairs
  • Three culvert repairs
  • Intermittent grading work
  • Repainting the fence along Coalmine Road

 

Questions?   Contact Sturgeon County offices, 780-939-8252 or email Roads@SturgeonCounty.ca

 