Approximately 500 m of Thin Lift Overlay will be applied on Viscount Crescent and 500 m will be applied to Viscount Drive from Sturgeon Road to Viscount Crescent.

Learn more about the Thin-Lift Asphalt Overlay process.

 

Project Update

October 1, 2021

Current status: Scheduled for completion by October 31, 2021.

September 24, 2021

Construction work on the Pavement Preservation program is anticipated to start the week of October 4, 2021, with crews travelling to work sites in the following order:

  1. Green Acres
  2. Manor Estates
  3. Upper Viscount
  4. Sturgeon Road East
  5. Twp Rd 554
  6. Benjamin Road
September 13, 2021

Construction is now scheduled to start on October 20, 2021.

September 7, 2021

Construction is scheduled to start on October 13, 2021.

August 2021

The tender closed on August 6, 2021.

Work is scheduled to begin in September 2021.