Access Fibre (runs by each premise in a subdivision, hamlet or industrial park)
- CFOC will be completing the last access point in early June.
- All other access construction is complete.
Drop fibre (connects the access fibre to the premise)
- Crews will be working in the Meadowview Drive area.
- Remaining drops require special installation procedures.
Splicing (connecting the fiber segments into one continuous length)
- Pro North is still in progress, all other splicing is complete.
ONT installation (the last step before service is available to a premise)
- ONT installations are being booked for communities included in Phase 1.
- Once your drop installation is complete you are ready to contact Canadian Fibre Optics Corporation to have your Optical Network Terminal (ONT) installed and activated, 1-888-236-2947