Hewitt Estates & Surgeon Valley Vista

Project Description

The Project

A Sturgeon County contractor will be upgrading the existing roads in Hewitt Estates and Sturgeon Valley Vista this summer, replacing it with a newly paved surface.

The Scope

Hewitt Drive and Valley Drive are scheduled to undergo a mill and overlay treatment, which involves removing the top layer of asphalt and replacing it with a new layer.
Abby Drive, Rex Place, Park Lane, and Marshall Place will receive a micro-surfacing treatment. This involves applying a new, thin layer of protective material on the road’s surface.

What this Means to You

There will be Sturgeon County project personnel, contractor crews, and equipment working in the project area. There will be temporary one lane closures with detour signs in place. Access to your home will be maintained throughout construction, but delays may occur.

Related Documents

Resident letter: October 18, 2025

Resident letter: June 7, 2024

Updates

  • November 1, 2024: Suspended for winter
    November 1, 2024

    Remaining deficiency repairs will need to be moved to the spring when conditions allow.

  • October 25, 2024: Completion date
    October 25, 2024

    Some remaining deficiency repairs will need to be moved to the spring when conditions allow.

  • October 15, 2024: Deficiency repairs
    October 16, 2024

    The contractor has returned to the site to work on some smaller spot repairs. Larger deficiencies, which need a paving until, will need to be postponed until spring now that the weather is not conducive to this type of work.

  • October 11, 2024: Project update
    October 11, 2024

    The construction crews are steadily working on this project. While there are no specific updates this weeks, we will keep you informed as these project progress.

  • September 13, 2024: Core project done
    September 13, 2024

    The core scope of the project is done, only deficiency repairs remain.

  • August 16, 2024: Work update
    August 16, 2024

    This project is now complete, although the contractor has clean up work to finish.

  • August 6, 2024: Hewitt Estates
    August 6, 2024

    Construction crews have finished moving equipment to the site. One-lane closures will be necessary, but a detour will not be required.

  • July 15, 2024: Paving update
    July 15, 2024

    Paving in Dover Estates is done. Crews will begin million in Hewitt Estates on July 16, 2024.