- Project category: Gravel Roads
- Division: Division 2
- Status: Complete
Project Description
Sturgeon County has determined that the existing 185-metre section of light pavement on Maple Street has deteriorated, resulting in rough and unsafe surface conditions for traffic and for upcoming winter maintenance.
Project scope
Three specific areas on the street will be completely rebuilt from the base to the surface. This work will address the localized sub grade issues, and the surface overlay over the 185-metre section will provide a complete, renewed asphalt surface.
What this means to you
A single lane of traffic will remain open while the work is underway. Please follow posted traffic signs and travel safely through the area. The work, being done by a contractor, is expected to take four to five working days to complete.
Related documents
Updates
-
September 25, 2024: Project doneSeptember 25, 2024
Repairs on Maple Street are now done.
-
September 10, 2024: Revised start dateSeptember 10, 2024
The contractor has informed Sturgeon County that they will begin work on this project on September 20, 2024. Weather permitting, they anticipate the core scope of work will be done on September 22.
-
August 19, 2024: Start dateAugust 19, 2024
Work on this project could begin on August 26 – weather permitting.