Project Highlights
The Project
A 500 metre section of E Estates Way will be upgraded from a gravel surface to a paved surface. This will require reconstructing and widening the road. Construction is planned for summer 2023, and weather permitting, completion by October 2023.
The Scope of Work
- Reconstructing, widening, and surfacing the road with asphalt.
- Minor upgrading and drainage improvements within the right-of-way.
What This Means to You
Heavy equipment will be in the area, there is the possibility of some traffic disruptions. Signs will be in place.
Location
Project Updates
-
October 20, 2023
Crews are now paving Estate Way from Park Road to Range Road 225 and adding the road lines.
-
May 11, 2023
Project page created.