- Category
- Roads
Project Highlights
Bridge maintenance is planned on a number of structures throughout the County this year as needs are identified. Currently, maintenance work is underway on Bridge File 00316, located on Township Road 562 west of Highway 44.
Location
Project Updates
-
July 11, 2022
This project is done.
-
March 31, 2022
Completed repairs:
- Bridge deck
- Bridge girder patch
- Gravel build up removal
- Miscellaneous other repairs
-
Complete:
- Gravel blockage causing drainage issues.
Background
- Bridge structures are inspected by certified inspectors on various inspection cycles. During inspections and through various reports and observations, an annual Bridge Maintenance Contract is developed and identifies structures to repair.
- This is classified as a standard bridge, on timber treated substructure constructed in 1958. Repairs to this bridge were completed in March 2022.