Project Highlights

This project involves the installation of a new bridge culvert, and is being done along with improvements to the Villeneuve Drainage Channel.

(Site 2 BF85401)

Project Updates

  • September 6, 2022

    The approach construction is underway. The culvert is scheduled to be installed in October.

  • August 11, 2022

    Construction on this project has started.

  • July 11, 2022

    The project has been awarded.