Project Highlights
In 2021, work started on drainage improvements to mitigate the risk of flooding in the community. The County hired WSP as the consulting engineer for this project.
The project involves assessing the existing wetlands and constructing a drainage ditch to improve drainage through the community. The concept of creating a pond facility in the reserve lot at the northeast side of the community is being considered. A retention pond would hold the runoff from rain and snowmelt and slowly release it downstream. These ponds can reduce the risk of flooding in the community.
Questions? Contact Joseph Areghan, Engineering Manager, by phone 780 939 1394 or by email at jareghan@sturgeoncounty.ca
Information Session
An information session was hosted on Wednesday, June 30, 2021, at 6:30 p.m. to provide an overview of the projects, introduce the project team and a brief Q&A session. You can watch a recording of the presentation here.
Questions? Contact Mark Guerette, Sr. Infrastructure Engineering Officer, at 780-939-1324 or by email at mguerette@sturgeoncounty.ca
Location
Project Updates
-
November 22, 2022
Construction is scheduled to begin in 2023.
-
July 11, 2022
A wetland assessment is underway.
-
October 22, 2021
Construction has been moved to 2022.
-
October 8, 2021
Tender review underway.
-
October 1, 2021
No change.
-
September 24, 2021
No change.
-
September 20, 2021
No change.
-
September 13, 2021
Crews are focused on completing the downstream improvements in 2021.
-
September 7, 2021
Construction is anticipated to start in fall 2021.
-
August 31, 2021
The competition has closed, and tenders are being reviewed.
Construction to start in fall 2021.