Fort Augustus Subdivision – road rehabilitation

Category
Roads

Project Highlights

Work involves rehabilitating the existing paved road network in Fort Augustus.

Fort Augustus Park Subdivision Rehabilitation project includes:​

  • 1.07 kilometres of road rehabilitation ​
  • Minor subgrade repairs to fix frost heaves ​
  • Two centre line culvert replacements

What to expect

Work sequence:​

  • Pulverize and widen existing surface​
  • Replace centre line culverts​
  • Place Granular Base Course (GBC)​
  • Spraying GBC with oil tack coat ​
  • Paving surface with hot mix asphalt​
  • General site cleanup​
  • Approaches will be getting paved up to the property line​

The construction zone will be limited to one lane with flaggers on site. In the evenings, the road will be opened to two-way traffic.

 

Location

Project Updates

  • July 25, 2022

    The project is done.

  • July 18, 2022

    Paving is scheduled to be done in July.

  • July 11, 2022

    Paving is scheduled to begin in mid-July.