2023 – Cunningham Bridge (east of Rge Rd 261) – bridge rehabilitation

Category
Roads

Project Highlights

Located on Meadowview Drive east of Rge Rd 261, Bridge File (BF) 02212 is an existing two-span girder bridge on a concrete substructure crossing the Sturgeon River. This location was identified as a priority crossing due to its age and condition.

The rehabilitation to the 65-year-old Cunningham Bridge is comprehensive and will extend its service life for an estimated 25 years. Phase 2 of the project is scheduled for April / May 2023.

For safety reasons, the bridge will need to be temporarily closed to all traffic during construction work from April 18 until June 9, 2023. A single lane will open to traffic, with barricades and signals, on June 10 until July 22, 2023.

Weather permitting, rehabilitation is expected to be done by July 27, 2023.

Project Updates

  • May 24, 2023

    Work ending the week of May 19 included:

    • Setting the joint rebar, including doweling, into the deck.
    • Sandblasting the concrete.
    • Setting deck joints.
    • Pouring HPC concrete.
  • May 15, 2023

    Work completed this past week includes:

    • Rebar was installed for the approach slabs.
    • Concrete was poured for the approach slabs, deck repairs, and abutment repairs.
    • Crews prepped joins for joint replacements.
  • May 5, 2023

    Construction crews continued with the backfill for the approach slabs. Concrete was removed at the abutments for repairs and near the joints. The deck rebar was sandblasted to get ready for concrete placement.

  • April 28, 2023

    Construction crews are working on various concrete repairs to the bridge. 

  • April 18, 2023

    A temporary full closure of the bridge is planned from April 18, 2023 to to May 23, 2023. The bridge will open to single lane traffic on May 24 to around July 9.

  • March 2, 2023

    Construction crews have started the first phase of the bridge rehabilitation project. This is expected to last for two weeks. To allow crews to safely carry out the work, the bridge is temporarily closed to all traffic until March 12, 2023.

  • October 3, 2022

    A tender has been awarded for the construction to be done in 2023.

  • September 6, 2022

    Major rehabilitation to this bridge has been identified.

  • August 15, 2022

    Tender closed August 15, 2022.

May 18, 2023

May 18, 2023

May 9, 2023

May 9, 2023.

Friday, May 5, 2023
Repairs to Cunningham Bridge

Friday, May 5, 2023
Repairs to Cunningham Bridge