Project Highlights
Located on Meadowview Drive east of Rge. Rd. 261, Bridge File (BF) 02212 is an existing two-span girder bridge on a concrete substructure crossing the Sturgeon River. This location was identified as a priority crossing due to its age and condition.
The rehabilitation to the 65-year-old Cunningham Bridge is comprehensive and will extend its service life for an estimated 25 years.
The bridge is now fully open! Thank you for your patience while we worked to improve and maintain Sturgeon County’s infrastructure.
Project Updates
-
August 8, 2023
The Cunningham Bridge rehabilitation project is now done!
Work from the final week included:
- The completion inspection was done.
- Project signage was removed.
- Minor work was completed.
- The bridge is fully open.
-
July 21, 2023
This week, crews installed snow plow guards, finished grading and added topsoil for seeding. Line painting is scheduled for next week.
-
July 17, 2023
Work done over the past week includes:
- Finished crack repairs at the abutments and girders.
- Removed drain trough forms.
- Fixed cracks for curbs and girders.
- Corrected bridge rail posts.
- Installed remaining bridge rail / approach rail posts.
-
July 3, 2023
Some of the work done this past week: crews are finishing the approach rain grading, and sandblasting areas of the bridge to get ready for the finish.
-
June 27, 2023
The bridge is now open to single lane traffic! Construction crews are installing the guard rails and there’s some grading work still to be done.
-
June 9, 2023
A single lane of traffic is now open.
Work done this week on Cunningham Bridge included:
- Curing cover plate concrete.
- Bridge rail and approach rail installation.
- Waterproofing.
- Paving.
-
May 24, 2023
Work ending the week of May 19 included:
- Setting the joint rebar, including doweling, into the deck.
- Sandblasting the concrete.
- Setting deck joints.
- Pouring HPC concrete.
-
May 15, 2023
Work completed this past week includes:
- Rebar was installed for the approach slabs.
- Concrete was poured for the approach slabs, deck repairs, and abutment repairs.
- Crews prepped joins for joint replacements.
-
May 5, 2023
Construction crews continued with the backfill for the approach slabs. Concrete was removed at the abutments for repairs and near the joints. The deck rebar was sandblasted to get ready for concrete placement.
-
April 28, 2023
Construction crews are working on various concrete repairs to the bridge.
-
April 18, 2023
A temporary full closure of the bridge is planned from April 18, 2023 to to May 23, 2023. The bridge will open to single lane traffic on May 24 to around July 9.
-
March 2, 2023
Construction crews have started the first phase of the bridge rehabilitation project. This is expected to last for two weeks. To allow crews to safely carry out the work, the bridge is temporarily closed to all traffic until March 12, 2023.
-
October 3, 2022
A tender has been awarded for the construction to be done in 2023.
-
September 6, 2022
Major rehabilitation to this bridge has been identified.
-
August 15, 2022
Tender closed August 15, 2022.
The bridge rehabilitation project is done.
August 8, 2023
August 8, 2023
August 8, 2023
August 8, 2023
July 17, 2023
July 18, 2023


June 27, 2023
June 27, 2023
June 9, 2023
May 18, 2023
May 18, 2023
May 9, 2023
May 9, 2023
Friday, May 5, 2023
Friday, May 5, 2023