- Category
- Roads
Project Highlights
The Project
Meadowview Drive was built as part of the original range road system during the early part of the last century. The road had a clay and tree base with minimal ditches and drainage culverts.
This project involves the reconstruction and surfacing of Meadowview Drive from Highway 44 to Range Road 263A as well as from Range Road 261A to the St. Albert boundary.
Construction for Phase 2 and Phase 3 (about 4.3 km) was started in summer 2022, the remaining work will be done in summer 2023. Paving will begin east of Cunningham Bridge on May 29. Paving west of Reyda Vista subdivision will be done after that.
Rehabilitation of Meadowview Drive from Range Road 261A to 263B was completed in summer 2022.
The Scope of Work
- Asphalt removal
- Earthworks and grading
- Base and paving
- Rebuilding existing residential/farm approaches
- Ditch rehabilitation/cleaning
What This Means to You
The traffic accommodation plan will be done to ensure that one lane is always open during the work hours, as well as providing access to residences throughout the project. Residents will be notified in advance if their access will be blocked.
Residents will be provided with a contact number in case there are any concerns.
Location
Project Updates
-
August 9, 2023
Crews have finished the line painting, and the guardrails have been installed. The project is nearing completion.
-
July 27, 2023
The project is just about done. There are still a few jobs left such as line painting, putting in permanent traffic signs and installing fences.
-
June 9, 2023
The paving work continues along Meadowview Drive.
-
June 5, 2023
Paving along Meadow Drive continues.
-
May 18, 2023
Paving east of Cunningham Bridge is scheduled to begin on May 29. Paving west of Reyda Vista Subdivision will be done after that.
-
November 22, 2022
The work scheduled for 2022 is now done. In 2023, work will include finishing the paving, final landscaping work, and cleaning the site. This work will begin once the frost is out of the ground.
-
October 26, 2022
Phase 1: The construction is done, and the inspection is also complete.
Phase 2: The gravel is being put down on the east section. Paving on the west section is underway.
-
September 6, 2022
The grading work is in progress on the east stretch of the project (Phase 2).
-
August 29, 2022
Phase 1 construction is done. Phase 2 subgrade work is now underway.
-
August 22, 2022
Seeding that is part of Phase 1 is now done. Subgrade work that is part of Phase 2 is underway.
-
July 11, 2022
The second lift of asphalt started on Monday. The plan is to complete the main alignment with the approaches to be finished later.
-
August 15, 2022
Identifying utility locations for Phase 2 is underway, along with tree clearing. Subgrade excavation on the east section is in progress.
-
July 18, 2022
Phase 1 paving and line painting is complete. Phase 2 utility relocation and tree clearing are in progress.
August 9, 2023
August 9, 2023
June 9, 2023.
June 9, 2023.