Lily Lake Road – Twp Rd 580 to Twp Rd 583 – pavement preservation

Category
Roads

Project Highlights

An extensive microsurfacing program is planned for several paved roadways in 2022, including: Township Road 570 from Range Road 215 to 224, Lily Lake Road from Township Road 580 to 583, Opal Road from Township Road 574 to 580, Range Road 275 north of Township Road 544 to the CN tracks, Range Rd 223 north of Boysdale Road, the Noroncal Subdivision, the Aspen Ridge Subdivision, and the Rosal Acres Subdivision.

What to Expect

  • As construction progress, intermittent locations will be reduced to one lane with ongoing traffic accommodation present.
  • Sturgeon County will be sending construction notification letters to affected residents prior to commencement of this work. If there are concerns, there will be a contact number to reach out prior to or during construction.
  • With favourable weather and barring additional COVID related disruptions, the work is anticipated to be complete by August 2022.

Location

Project Updates

  • July 11, 2022

    This project is done.

  • June 13, 2022

    Pavement Preservation starts on June 13, completion in 2022.

Background

  • Pavement Preservation encompasses two different treatment types in 2022:
    • Micro-Surfacing
    • Mill and Overlay
  • Micro-surfacing
    Micro-surfacing is the application of a special coating to the top layer of asphalt that prevents oxidization and moisture penetration. The components are mixed on site and spread onto the road surface.
  • Mill and Overlay
    Mill and Overlay is a multi-stage process that involves removing a specified thickness of asphalt using a million machine, and then paving over top of the milled surface.
  • This project includes:
    • Lily Lake Road from TWP 580 – 583 — Micro-Surfacing
    • Aspen Ridge Subdivision — Micro-Surfacing