Opal Road – Twp Rd 574 to Twp Rd 580 – pavement preservation

Category
Roads

Project Highlights

An extensive microsurfacing program is planned for several paved roadways in 2022, including: Twp Rd 570 from Rge Rd 215 to 224, Lily Lake Road from Twp Rd 580 to 583, Opal Road from Twp Rd 574 to 580, Range Road 275 north of TWP 544 to the CN tracks, Rge Rd 223 north of Boysdale Road, the Noroncal Subdivision, the Aspen Ridge Subdivision, and the Rosal Acres Subdivision.

What to expect

  • Sturgeon County will maintain one lane of traffic throughout the duration of the project. If a road closure is required residents will be notified in advance. If there are concerns, residents will have a contact number to reach out prior to the work taking place.
  • Micro-Surfacing projects will be completed one week after commencement.
  • Mill and Overlay projects will be completed three weeks after work begins.

Location

Project Updates

  • July 11, 2022

    This project is done.

  • June 13, 2022

    Pavement Preservation starts on June 13, completion in 2022.

Background

  • Pavement Preservation encompasses two different treatment types in 2022
    • Micro-Surfacing
    • Mill and Overlay
  • Micro-Surfacing
    Micro-Surfacing is the application of special coating to the top layer of asphalt that prevents oxidization and moisture penetration. The components of the mixture are mixed on site and spread onto the road surface.
  • Mill and Overlay
    Mill and Overlay is a multi stage process which involves removing a specified thickness of asphalt using a milling machine, and then paving over top of the milled surface.
  • The project includes:
    • Township Road 570 from Range Road 215 – 224 — Micro-Surfacing
    • Opal Road from Township Road 574 – 580 — Micro-Surfacing