Project Highlights
Road rehabilitation will take place along Range Road 251 between Sturgeon Heights Subdivision and the St. Albert border.
Project Updates
-
November 26, 2021
Current status: The 2021 construction season has ended. Any remaining work will carry over to 2022.
-
November 12, 2021
Construction is substantially complete with some additional drainage work in progress
-
November 5, 2021
Construction is underway with subgrade work in progress.
-
October 1, 2021
Construction is underway. Stripping commenced.
-
September 24, 2021
Construction is set to begin after substantial completion of the project on TWP 542.
-
September 13, 2021
Construction is set to begin after substantial completion of the project on TWP 542.
-
September 7, 2021
Construction is scheduled to start in mid-September, with crews mobilizing equipment on site the week of September 13, 2021.
-