Road Rehabilitation – Rge Rd 251 – Sturgeon Heights Subdivision to St. Albert

Project Highlights

Road rehabilitation will take place along Range Road 251 between Sturgeon Heights Subdivision and the St. Albert border.

Project Updates

  • November 26, 2021

    Current status: The 2021 construction season has ended. Any remaining work will carry over to 2022.

  • November 12, 2021

    Construction is substantially complete with some additional drainage work in progress

  • November 5, 2021

    Construction is underway with subgrade work in progress.

  • October 1, 2021

    Construction is underway. Stripping commenced.

  • September 24, 2021

    Construction is set to begin after substantial completion of the project on TWP 542.

  • September 13, 2021

    Construction is set to begin after substantial completion of the project on TWP 542.

  • September 7, 2021

    Construction is scheduled to start in mid-September, with crews mobilizing equipment on site the week of September 13, 2021.