Pine Sands Subdivision – road reconstruction

Category
Roads

Project Highlights

This summer, Sturgeon County is starting work to reconstruct and pave the roads in the Pine Sands Subdivision.

The project to reconstruct the 2.5 km of roads within the Pine Sands Subdivision began in 2021.​ The roadways are of mixed surface type, in moderate to poor condition.​ ​The County has undertaken the project to improve the surfaces and roadway structure to current construction standards.​

The project includes:​

  • Grading​
  • Granular base course​
  • Surface paving

What to expect

Sturgeon County will be sending construction notification letters to affected residents before the work begins. A contact number will be provided in case there are concerns.

There will be traffic disruptions in the work zone. One lane traffic will be maintained, as well as access to residences during the project.​

A tentative schedule of construction will be included within the notification letter.

Location

Project Updates

  • September 6, 2022

    The contractor is expected to restart in early September 2022.

  • August 11, 2022

    The project is now scheduled to begin in August 2022.

  • July 11, 2022

    The work is scheduled to begin mid-July. Notices have been sent to residents.