2023 – Pinnacle Ridge: slope repair

Category
Roads

Project Highlights

Work will repair and stabilize the slope adjacent to the walking trail in Pinnacle Ridge. The gravel trail is open for use, but will close when it becomes too muddy with the spring 2023 thaw. The path will then remain closed until the construction is completed. Work is expected to be done by the end of June 2023.

Location

Project Updates

  • July 19, 2023

    The project is almost finished; a fence needs to be put up, and seeding is required.

  • June 12, 2023

    Construction crews are paving the trail today, and it should be open for use tomorrow (June 13).

    Crews still need to finish up some minor landscaping and putting in a fence.

  • May 24, 2023

    Construction done in the previous week includes:

    • slope repair is done,
    • surface drainage earthwork is done, and
    • final grading and landscaping is in progress.

    The remaining work includes erosion control blanket and hydro seeding, trail paving, and fence installation.

  • May 5, 2023

    Construction on this project continues as scheduled.

  • May 2, 2023

    Work started again on May 2, 2023. The end of June is still the anticipated completion date.

  • November 22, 2022

    It is anticipated that the project will be 90 per cent done in 2022. The remaining landscaping and trail paving will now happen in 2023.

  • October 26, 2022

    Construction is in progress. It is anticipated the project will be done in 2022.

  • October 3, 2022

    The completion of this project is still scheduled to be in 2022.

  • August 11, 2022

    Design work for this project is underway.

  • June 13, 2022

    Design contract fully executed.