Sturgeon Crest Subdivision – road rehabilitation

Category
Roads

Project Highlights

As part of Sturgeon County’s 4-Stage Capital Plan, Sturgeon Crest Subdivision has been identified for rehabilitation and is scheduled for construction in 2022. ​ The project team is currently determining the desired rehabilitation strategy for the subdivision​.

The project includes:​

  • The road rehabilitation of 1.0 km within the subdivision​

What to expect

Work sequence:​

  • Pulverize and widen existing surface​
  • Replace centre line culverts​
  • Place Granular Base Course (GBC)​
  • Spraying GBC with oil tack coat ​
  • Paving surface with hot mix asphalt​
  • General site cleanup​
  • Approaches will be paved up to the property line​

Construction zone will be limited to one lane with flaggers on site. In the evenings, the road will be opened to two-way traffic.

Location

Project Updates

  • November 21, 2022

    The paving for this project is done. The landscaping and site-cleanup will happen in 2023.

  • October 26, 2022

    It is anticipated the construction will be done in October.

  • September 27, 2022

    Construction is in progress.

  • September 6, 2022

    Construction is scheduled to start the week of September 6, 2022.

  • August 29, 2022

    Construction will begin after the Labour Day long weekend.

  • August 11, 2022

    Construction is scheduled to start on August 22, 2022.

  • July 11, 2022

    The contract has been awarded. Work is scheduled to begin in late August with completion in 2022.