Project Highlights
This summer, the parts of the following roadways will be reconstructed:
- Twp Rd 544 (Hwy 2 to Elliot Street (Access to ProNorth)
- Rge Rd 252 (Hwy 37 to Coal Mine Road)
This project includes paving both roads with asphalt surfacing.
Project Updates
-
July 4, 2022
The first lift of asphalt is done with the exception of one section requiring repairs on Range Road 252. Subgrade work on Twp Rd 544 ProNorth is in progress.
-
June 27, 2022
The first lift of asphalt of Twp Rd 544 from the firehall road is in progress. Subgrade work on Twp Rd 544 ProNorth is in progress.
-
June 13, 2022
Construction crews are finishing work near the south limits of the firehall. The equipment relocation and paving at ProNorth is scheduled to be done by the end of July.