- Project category: Paved Roads
- Division: Division 2
- Status: In progress
Project Description
The Project
The project will involve the full reconstruction and surfacing of Coal Mine Road with new asphalt. The project limits are from west of Township Road 544 to east of Estate Way Drive (1.8 kilometres). The intersection of Township Road 544 and Coal Mine Road will be realigned to improve the approach angle and sight lines. Weather permitting, the project should be done by the end of July.
Range Road 252 from Bellerose Drive to Coal Mine Road will be reconstructed and paved (0.9 kilometres), and the intersection with Bellerose Drive will be upgraded.
The Scope of Work
- In spring 2023, the contractor will be working west from Range Road 252 north and then working on the intersection upgrades at Bellerose Drive and Township Road 544.
- Most of the grading along Range Road 252 is done.
- Grading along Coal Mine Road east of Range Road 252 north is done.
What This Means to You
There is the potential for disruptions to traffic flow. Traffic signs will be in place.
Updates
-
July 14, 2023: Project page created.July 14, 2023
The grading work continues along Coal Mine Road. The intersection upgrade work is scheduled to begin in late July, weather permitting. The gravel and pavement will be added once the grading is complete.
-
Road Closure ExtendedAugust 28, 2023
The road closure of Range Road 252 has been extended to September 24 as grading continues along Coal Mine Road and Range Road 252 C. This work is scheduled to be done by late September, weather permitting.
-
Paving UnderwayOctober 13, 2023
Paving work is underway on this project.
-
Final Landscaping and Clean-UpMay 20, 2024
Final landscaping and cleanup work will commence in mid-May. Traffic accommodation will be in place to ensure safe passage through the construction stie. This work is expected to be done by mid-June.